Project Direction Map

            For larger condominium and apartment projects, the builder should consider installing a direction map board at the main entrance into the project.

            This activity should be completed about the same time as the sales models grand opening, installed concurrent with the sales models complex landscaping.

            On a particular 282-unit condominium project, the U-shaped buildings had their entry doors and address numbers on the outside perimeter of each 12-unit building, one floor level above a central motor courtyard and above street level.

            People driving into the project had no way of finding the house address numbers without getting out of their cars and walking around the buildings. 

            Not only was it difficult for visitors to find their way around the project, but delivery companies had problems as well. 

From Lessons-Learned for Builders, Architects, and Interior Designers in Housing Construction, Book 6.

Author: Barton Jahn

I worked in building construction as a field superintendent and project manager. I have four books published by McGraw-Hill on housing construction (1995-98) under Bart Jahn, and have eight Christian books self-published through Kindle Direct Publishing (KDP). I have a bachelor of science degree in construction management from California State University Long Beach. I grew up in Southern California, was an avid surfer, and am fortunate enough to have always lived within one mile of the ocean. I discovered writing at the age of 30, and it is now one of my favorite activities. I am currently working on more books on building construction.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: